After several delays (mainly caused by bad weather, contractor delays, and Christmas!) we’ve finally had the footings dug out and concrete poured for the generator enclosure.
The grass banking was dug out on Tuesday 23rd, and concrete poured Thursday 25th. Blockwork has been delivered and the enclosure itself is scheduled to be constructed next week. Once the encloure is complete we’ll pull the thick generator cables through and move the generator itself into position.
We’re confident that (if there’s no more snow – which apparently doesn’t help concrete set!) the generator will be in position mid-March!

Digging out the footings

Ready for concrete

Concrete finally poured!

The generator, in storage. Waiting to be positioned.