Less than a month after construction started, the final plastering has been completed and the decoration has started throughout. Elsewhere Openreach have been in to terminate the 10-pair copper which will be used for phone lines, DSL, and the redundant access services. The access-control controller boxes are being configured, and finally the 2nd fix electrics in the office are now going in.
This week promises to be a milestone in the project – not only will Friday be the one-month-marker, but the raised floor is due on site. Before the end of the Bank Holiday we hope to have the raised floor in place where racks 1 and 2 will go, so Openreach and Telewest can come in and terminate the fibre from next week.

Final plastering complete

Decoration well under way

Office second fix electrics

Openreach on site