Pics of the fibre B-Side install by Openreach…

Openreach on site again...

Fibre jointing in the street

B-End fibre termination
Pics of the fibre B-Side install by Openreach…

Openreach on site again...

Fibre jointing in the street

B-End fibre termination
BT Openreach were on site yesterday to install the B-Side of our 100Mbit fibre connection to Virgin Media.
The fibre installation at our end went smoothly, and Openreach have left a loop connector in place so they can begin loopback testing from the A-Side (at Virgin Media / Telewest / NTL).
Elsewhere on site more raised access floor has been layed, and more wiring for emergency lights, CCTV and security has been installed.
Pics to follow soon!!
Less than a month after construction started, the final plastering has been completed and the decoration has started throughout. Elsewhere Openreach have been in to terminate the 10-pair copper which will be used for phone lines, DSL, and the redundant access services. The access-control controller boxes are being configured, and finally the 2nd fix electrics in the office are now going in.
This week promises to be a milestone in the project – not only will Friday be the one-month-marker, but the raised floor is due on site. Before the end of the Bank Holiday we hope to have the raised floor in place where racks 1 and 2 will go, so Openreach and Telewest can come in and terminate the fibre from next week.

Final plastering complete

Decoration well under way

Office second fix electrics

Openreach on site