While most people have been eating chocolate eggs, our team have been busy over the Easter break pressing on with construction in order to meet our June deadline. Thanks go out to all involved over the Bank Holiday!
We’ve now removed all the original wiring from the unit, and temporay lights + sockets have been installed, all the computer room and office ceilings have been borded ready for finishing, the entrance hall has been boarded, and construction of the loading bay has begun.
We also got our first real look above the computer room ceiling. This is where the air conditioning condenser units will go, recycling and cooling the air in the roof void rather than air from outside. Not only will this enable us to use less power for cooling, but will help create a constant environment in the whole building, recycling the hot air removed from the computer room.

Temporary lights and sockets

Above the data centre

Office walls nearly complete


Into the entrance hall
Watch out for further updates during the week as work progresses!